1. Every class has a parameterless toString method which returns a String containing a dump or summary of an instance of the class.
|
|
|
|
|
|
|
|
|
**Action Plan**<br>
|
|
|
|
|
|
*Fantastic 4*:<br>
|
|
|
All team members had participated in two scheduled weekly meetings as usual.<br>
|
|
|
Alpha related issues had been discussed and resolved;
|
|
|
These two meetings were used as mostly workshop hours for this milestone. <br>
|
|
|
Time spent as a team: 2.5 hours (1.5 hours of Tuesday meeting, 1 hour of Thursday meeting, 2.5 hours in total)
|
|
|
|
|
|
Ali (Back-End): <br>
|
|
|
Worked closely with Jordan, completing about 50% of the database plus basic information of pages.<br>
|
|
|
Will continue to address issues regarding the Beta focuses 1, 2, & 4 as indicated above. <br>
|
|
|
Individual time spent on Milestone 8: 15 hours <br>
|
|
|
Individual time will be spent on Milestone 9: 10 hours
|
|
|
|
|
|
Jordan (Back-End): <br>
|
|
|
Scheduled and booked a team meeting room as a regular weekly task.<br>
|
|
|
Worked closely with Ali, completing about 50% of the database plus basic information of pages.<br>
|
|
|
Revised ReadMe file of the master branch and minor changes of the database.<br>
|
|
|
Will continue on resolving the Beta focuses 1, 2, & 4 as indicated above together with Ali. <br>
|
|
|
Individual time spent on Milestone 8: 15 hours <br>
|
|
|
Individual time will be spent on Milestone 9: 10 hours
|
|
|
|
|
|
Nick (Front-End): <br>
|
|
|
Completed testing of the database of the project created by Jordan and Ali.
|
|
|
Revised ReadMe file of the master branch together with Jordan after minor changes.
|
|
|
Worked on the styling of ejs pages: Homepage(index), Flights, Payment with required contents.<br>
|
|
|
Will continue to resolve issues regarding the Beta focus 3 and reaming Alpha focus 5, 6, 7 and 8 as indicated above. <br>
|
|
|
Individual time spent on Milestone 8: 8 hours <br>
|
|
|
Individual time will be spent on Milestone 9: 10 hours
|
|
|
|
|
|
Wes (Front-End): <br>
|
|
|
Created and summarized Milestone 8 at Wiki. <br>
|
|
|
Finished the final formatting of this milestone.<br>
|
|
|
Worked on the styling of ejs pages: Summary and About Page with required contents.<br>
|
|
|
Completed testing of Product Alpha with desired coverages, user stories 5 to 8. <br>
|
|
|
Will work closely with Nick tackling the Beta focus 3 and remaining Alpha focus 5, 6, 7 and 8 as indicated above. <br>
|
|
|
Individual time spent on Milestone 8: 8 hours<br>
|
|
|
Individual time will be spent on Milestone 9: 10 hours |
|
|