**Action Plan**<br>
|
|
|
|
|
|
*Fantastic 4*:<br>
|
|
|
All team members had participated in two scheduled weekly meetings as usual. Alpha related issues had been discussed and resolved; These two meetings were used as mostly workshop hours for this milestone. <br>
|
|
|
All team members had participated in two scheduled weekly meetings as usual.
|
|
|
Alpha related issues had been discussed and resolved;
|
|
|
These two meetings were used as mostly workshop hours for this milestone. <br>
|
|
|
Time spent as a team: 2.5 hours (1.5 hours of Tuesday meeting, 1 hour of Thursday meeting, 2.5 hours in total)
|
|
|
|
|
|
Ali (Back-End): <br>
|
... | ... | @@ -84,7 +86,7 @@ Individual time will be spent on Milestone 9: 10 hours |
|
|
Nick (Front-End): <br>
|
|
|
Completed testing of the database of the project created by Jordan and Ali.
|
|
|
Revised ReadMe file of the master branch together with Jordan after minor changes.
|
|
|
Worked on the following pages: Homepage(index), Flights, Payment with required contents.
|
|
|
Worked on the styling of ejs pages: Homepage(index), Flights, Payment with required contents.
|
|
|
Will continue to resolve issues regarding the Beta focus 3 and reaming Alpha focus 5, 6, 7 and 8 as indicated above. <br>
|
|
|
Individual time spent on Milestone 8: 8 hours <br>
|
|
|
Individual time will be spent on Milestone 9: 10 hours
|
... | ... | @@ -92,7 +94,7 @@ Individual time will be spent on Milestone 9: 10 hours |
|
|
Wes (Front-End): <br>
|
|
|
Created and summarized Milestone 8 at Wiki. <br>
|
|
|
Finished the final formatting of this milestone.<br>
|
|
|
Worked on the following pages: Summary and About Page with required contents.
|
|
|
Worked on the styling of ejs pages: Summary and About Page with required contents.
|
|
|
Will work closely with Nick tackling the Beta focus 3 and reaming Alpha focus 5, 6, 7 and 8 as indicated above. <br>
|
|
|
Complete testing of Product Alpha.
|
|
|
|
... | ... | |