... | ... | @@ -69,7 +69,7 @@ Time spent as a team: 2.5 hours (1.5 hours of Tuesday meeting, 1 hour of Thursda |
|
|
|
|
|
Ali (Back-End): <br>
|
|
|
Worked closely with Jordan, completing about 50% of the database plus basic information of pages.<br>
|
|
|
Will continue to address issues regarding the Beta focuses 1, 2, & 4 as indicated above<br>
|
|
|
Will continue to address issues regarding the Beta focuses 1, 2, & 4 as indicated above. <br>
|
|
|
Individual time spent on Milestone 8: 15 hour<br>
|
|
|
Individual time will be spent on Milestone 9: 10 hours
|
|
|
|
... | ... | @@ -84,19 +84,17 @@ Individual time will be spent on Milestone 9: 10 hours |
|
|
Nick (Front-End): <br>
|
|
|
Completed testing of the database of the project created by Jordan and Ali.
|
|
|
Revised ReadMe file of the master branch together with Jordan after minor changes.
|
|
|
Worked Five basic pages: Homepage(index), Flights, Payment, Summary, and About Page
|
|
|
with required contents (minimum 4 user stories for this milestone),
|
|
|
photos, text box, click buttons, date picker, etc, of all 8 user stories.
|
|
|
Will continue to resolve issues regarding Beta focus 3, 5, 6, 7 and 8 as indicated above<br>
|
|
|
Worked on the following pages: Homepage(index), Flights, Payment with required contents.
|
|
|
Will continue to resolve issues regarding the Beta focus 3 and reaming Alpha focus 5, 6, 7 and 8 as indicated above. <br>
|
|
|
Individual time spent on Milestone 8: 8 hours <br>
|
|
|
Individual time will be spent on Milestone 9: 10 hours
|
|
|
|
|
|
Wes (Front-End): <br>
|
|
|
Created and summarized Milestone 8 at Wiki. <br>
|
|
|
Finished the final formatting of this milestone.<br>
|
|
|
|
|
|
Will work closely with Nick on the creation of HTML pages with CSS styling and the connection between the database and HTML pages for next milestone.<br>
|
|
|
Complete testing of Alpha.
|
|
|
Worked on the following pages: Summary and About Page with required contents.
|
|
|
Will work closely with Nick tackling the Beta focus 3 and reaming Alpha focus 5, 6, 7 and 8 as indicated above. <br>
|
|
|
Complete testing of Product Alpha.
|
|
|
|
|
|
Individual time spent on Milestone 8: 8 hours<br>
|
|
|
Individual time will be spent on Milestone 9: 10 hours |
|
|