... | ... | @@ -49,65 +49,65 @@ For this milestone, Zhong described the project's goal and preliminary design, a |
|
|
For next week, we will work together with the user stories, probably every member provide one epic.
|
|
|
The project is expected finished around final time, it is a large work so we need to fight together to achieve our goal.
|
|
|
|
|
|
Milestone plan:
|
|
|
**Milestone plan:**
|
|
|
|
|
|
General instruction: It is hard to assign what everyone should do in each milestone at this time. As a result, our group will just have a rough plan about what each member will do in the next few milestones. Basically, we will do all the parts together because we are a group. We will communicate with each other regularly and have one or two group meeting every week. Rough plan for each group member: Zhong and Zhang will focus more on the parts of design of the website by using html. Liu and Li will focus more on how to connect everything with our database by using Javascript.
|
|
|
|
|
|
Milestone 1: Company Registration
|
|
|
**Milestone 1: Company Registration**
|
|
|
|
|
|
Expected dates:Finished
|
|
|
|
|
|
Expected hours: 5 hours
|
|
|
|
|
|
Milestone 2: Production Selection
|
|
|
**Milestone 2: Production Selection**
|
|
|
|
|
|
Expected dates:Finished
|
|
|
|
|
|
Expected hours: 4 hours
|
|
|
|
|
|
Milestone 3:Preliminary Requirement Overview
|
|
|
**Milestone 3:Preliminary Requirement Overview**
|
|
|
|
|
|
Expected dates: Jan 24th
|
|
|
|
|
|
Expected hours: 16 hours
|
|
|
|
|
|
Milestone 4:Detailed Requirement Overview
|
|
|
**Milestone 4:Detailed Requirement Overview**
|
|
|
|
|
|
Expected dates: Jan 30th
|
|
|
|
|
|
Expected hours: 75 hours
|
|
|
|
|
|
Milestone 5:Preliminary Design
|
|
|
**Milestone 5:Preliminary Design**
|
|
|
|
|
|
Expected dates: Feb 7th
|
|
|
|
|
|
Expected hours: 65 hours
|
|
|
|
|
|
Milestone 6:Detailed Design
|
|
|
**Milestone 6:Detailed Design**
|
|
|
|
|
|
Expected dates: Feb 14th
|
|
|
|
|
|
Expected hours: 120 hours
|
|
|
|
|
|
Milestone 7:Test Plan
|
|
|
**Milestone 7:Test Plan **
|
|
|
|
|
|
Expected dates: Feb 27th
|
|
|
|
|
|
Expected hours: 100 hours
|
|
|
|
|
|
Milestone 8:Product Alpha
|
|
|
**Milestone 8:Product Alpha**
|
|
|
|
|
|
Expected dates: Mar 6th
|
|
|
|
|
|
Expected hours: 65 hours
|
|
|
|
|
|
Milestone 9:Code Inspection and Improvement Plan
|
|
|
**Milestone 9:Code Inspection and Improvement Plan**
|
|
|
|
|
|
Expected dates: March 13rd
|
|
|
|
|
|
Expected hours: 85 hours
|
|
|
|
|
|
Milestone 10:Product Beta
|
|
|
**Milestone 10:Product Beta**
|
|
|
|
|
|
Expected dates: Mar 20th
|
|
|
|
... | ... | |